For a 100 MW utility-scale solar project, one of the first questions EPC contractors ask is:
How many solar installation robots are actually needed?
The answer depends on the project size, module type, installation schedule, and robot productivity.
However, a simple capacity calculation can provide a useful starting point.
Start with the Number of Solar Modules
A 100 MW solar farm may require approximately 160,000–200,000 modules, depending on the module power rating.
For example, with 550 W modules:
100 MW ÷ 0.55 MW per 1,000 modules ≈ 182,000 modules
The actual number will vary based on the selected module.
Then Consider Robot Productivity
Relu Robotics Bison is designed for utility-scale PV module installation and can achieve approximately 80–95 modules per hour under suitable site conditions.
Using 85 modules/hour as an example, with a typical 10-hour working day:
85 × 10 = 850 modules/day
At this rate, one robot could theoretically install a significant number of modules during a project.
For a 100 MW project with approximately 182,000 modules, the required number of robots can then be estimated based on the target installation period
Example: Different Project Schedules
Why the Number Can Vary
Robot quantity is not determined by MW alone.
EPC contractors should also consider:
- Module quantity and module size
- Target construction schedule
- Daily working hours
- Site terrain and accessibility
- Row spacing and ground clearance
- Module loading and material logistics
- Number of installation crews
- Robot utilization and site efficiency
For example, a 100 MW project with a tight construction schedule may require more robots, while a project with a longer installation window may achieve the same output with fewer units.
The Better Approach: Calculate by Daily Output
Instead of asking only “How many robots do I need for 100 MW?
EPC teams should calculate:
Required Robots = Total Modules ÷ Target Installation Days ÷ Daily Output per Robot
This provides a more practical estimate for project planning and equipment deployment.
Planning a 100 MW Solar Project?
Relu Robotics Bison is designed to support large-scale PV construction by automating repetitive module handling and placement while working alongside site operators.
For a project-specific robot quantity calculation, share your project capacity, module wattage, target installation period, and site conditions with the RELU team.
Be the first to comment.